| » Christmas in Atlantis - snow pics! |
 |
| ... More |
| » Summer 2009 |
 |
| ... More |
| » Febuary 2008 Update |
 |
| ... More |
| » July 2009 Update |
 |
| ... More |
| » June 2009 Update 2 |
 |
| ... More |
| » June 2009 Update |
 |
| ... More |
| » May 2009 Update |
 |
| ... More |
| » April 2009 Update 3 |
 |
| ... More |
| » April 2009 Update 2 |
 |
| ... More |
| » April 2009 Update |
 |
| ... More |
| » Janury 2009 Update 2 |
 |
| ... More |
| » Janury 2009 Update |
 |
| ... More |
| » 7 December 2007 |
 |
| Progress is continuing on Atlantis, with Block F reaching roof level in the last couple of days. Pictures attached.... More |
| » Block F now at third floor level, Block E glazing almost complete |
 |
| Here are the latest pctures from the building site. Block F has now reached third floor level, with Block E glazing almost complete. More pictures attached...... More |
| » 9th November 2007 |
 |
| Work continues on the common areas, as well as the apartments. Check out the latest photos.... More |
| » 12 October 2007 Block D being furnished |
 |
| Construction is now almost complete in Blocks A-D. Block D furniture will be going in soon. Block E is being glazed, and Block F is heading for first floor level.... More |
| » Update 1 Oct 07 |
 |
| The spa under Block F is now complete, and work is starting on the ground floor level. Work continues on the other blocks too, with Blocks A-D almost complete and Block E at roof level.... More |
| » Construction Update - 01.08.2007 |
 |
| Here are the lastest pictures from the Atlantis construction site.... More |
| » Update 31st July 2007 - Block E |
 |
| Block E is now at roof level. The extra space on top of Block E will be the sky bar and terrace.... More |
| » Atlantis update 26.7.07 |
 |
| Latest photos attached. More should follow shortly.... More |
| » Show Apartments - One bed |
 |
| Here are the shots of the one-bedroom show apartment in Block D.... More |
| » 5th July 2007 - Show apartments - Studio |
 |
These photos are of the actual show apartments in Atlantis, both in Block D. There is a studio & a one-bed show apartment. This gives an idea of the actual finish & furniture, although accessories shown are not included.... More |
| » 1st June 2007 - work has started on the main swimming pool |
 |
| ... More |
| » New photos of ABCD taken today! |
 |
| Here are the latest photos of Blocks ABC and D, taken on-site today. Glazing & internal works are well underway.... More |
| » Block E nearly at third floor level - May 2007 |
 |
| Work is going well on Atlantis Block E. Photographs attached...... More |
| » Update 28 March 2007 |
 |
| ... More |
| » More photos 13 March 2007 |
 |
| Work has now begun on Blocks E & F.... More |
| » Latest photos March 13 2007 |
 |
| Here are the latest photos from the Atlantis site. Blocks B & C are now started, and foundation work is beginning for blocks E & F.... More |
| » Construction Update - 12 Feb 2007 |
 |
| The construction work for Blocks E and F of Atlantis project is underway...See attached photos of building site.... More |
| » Construction Update - 09 January 2007 |
 |
| Here are some recent pictures showing Atlantis construction progress on 09 January 2007.... More |
| » Construction Update - 14 December 2006 |
 |
| Here are the latest pictures from the construction site, showing progress at 14 December 2006.... More |
| » Construction Update - 06 December 2006 |
|
| Here are the latest pictures taken from the construction site on 06 December 2006.... More |
| » Construction Update - 03 November 2006 |
|
| Here are the latest pictures showing progress for the Atlantis Development on 02 October 2006..
Block B and D complete to roof level. Block A foundations are now completed. The site is currently being cleared for the start of Block E and F.
... More |
| » Construction Update - 12th October 2006 |
|
| Construction work for Atlantis is progressing well...Block A has now been completed to roof level and the construction of Block B has now started.... More |
| » Construction Update 6th Sep 2006 |
|
Some more pics of the construction progress with the latest images of the site.
Block D is completed to roof level.
Block A will be completed to roof level by 18 September 2006.
Blocks B & C- It is planned to start foundations next week, w/c 18 Sep 2006.
Blocks E&F - The site is being cleared and making the circle around-fence, in the plot!
Starting to complete fondation at the start of October 2006.
... More |
| » Construction Update 1st Sep 2006 |
|
| The Atlantis construction work is progressing well..More details coming soon..... More |
| » Construction Update 12th July 2006 |
|
| Here are the latest pictures of the Atlantis project on 12th July 2006. Block D has reached roof level, and Block A has foundations completed and started ground floor building works.... More |
| » Atlantis Construction Progress Update- 7th July 2006 |
|
| The construction work for the Atlantis Apartments is now well underway..Block D is completed to roof level and Block A foundations are laid..... More |
|